Construction Updates


 Current Project Wide Status 
Week Ending 8/15/2010 

(updates are published bi-weekly)

Click here to view previous updates

Updated Schedule Progress

 

 

Click on the thumbnails below to view the enlarged photos. (Updated August 25, 2010)


Detour at Carpenter Fire Station Fine grading North of Green Level West Seed & Mulch being placed North of US 64 Storm Drain Installation North of Green Level West

Panther Creek - Pouring NB bridge deck Span A & B McCrimmon - Erecting girders on Span B Left White Oak - Pouring SB Bent #2 Cap with concrete pump US64 - Pile driving completed at End Bent #2 NB & SB

ROADWAYS:
(update posted August 25, 2010) 

Clearing & Grubbing

•Clearing and Grubbing continued from Apex BBQ to Old US1 
        

 

Erosion Control

•Installation of erosion control measures from Beaver Creek to Olive Chapel
 

Box Culvert

•Construction of Box Culvert between Olive Chapel and US 64

Earthwork

• Dirt Work (Fill) from Hwy 55 to Nancy Branch
• Dirt Work (Fill) from Green Hope Rd to Green Level West
• Dirt Work (Fill) from Green Level West to White Oak Creek
• Dirt Work (Fill) from White Oak Creek to Jacks Branch
• Dirt Work (Cut) from Jacks Branch to Roberts Rd
• Dirt Work (Fill) from US 64 to Green Level Church

 

Drainage

 

• Drainage Pipe from Carpenter Fire Station to McCrimmon
• Drainage Pipe from Green Level West to Green Hope
 
 

 

 

STRUCTURES
(Update posted August 25, 2010)

Bridges

• Nancy Branch: End Bent #2 NB & SB MSE Wall
• Nancy Branch: Installed overhang on NB side
• McCrimmon: Erected all concrete girders
• McCrimmon: Installation of MSE Walls
• Panther Creek: Poured both spans of NB Bridge Deck.
• White Oak Creek: Formed/Poured/Stripped columns at SB Bent #1. Formed SB Bents #2 and #1 caps. Poured SB Bent #2 cap
• US 64: Formed/Poured/Stripped Aesthetic Columns at Bent #2 NB. Finished SB Aesthetic Columns. Pre-augured and drove all piles at NB and SB End Bent #2
• Beaver Creek: Coastal Caisson installed drill shafts at Bent #7 SB, Bent #7 NB, Bent #6 SB, and Bent #6 NB. Completed trestle approach on north side.



 Utilities

• Construction Supervision Service Inc. is installing a 36” casing (Conflict 39) for Town of Apex proposed gravity sewer between Jenks and Roberts Road.
• AT&T completed the fiber optic relocation to the south side of Carpenter Fire Station Road and will splice the two copper lines this week.
• PSNC Gas contractor completed the relocation of the gas main north of Green Hope School Road and began relocation of the gas main north of Olive Chapel.
• Progress Energy crews will be working at Roberts Road and then move to Olive Chapel to begin clearing pending Right of Entry.
• Town of Apex Power began underground bore to re-route power through Beaver Creek at Site 11.