Construction Updates
Current Project Wide Status
Week Ending 1/27/12
(updates are published bi-weekly)
Click here to view previous updates
Updated Schedule Progress
(Right: Aerial Photo of US 64 & Kelly Road)
Click on the thumbnails below to view the enlarged photos. (Updated February 2, 2012)
Roll mouse over the photos before clicking to view description.
ROADWAYS:
(update posted February 2, 2012)
Bi-Weekly Overview:
- Robert’s Rd to I-540: Installed guardrail, backed shoulders, removed sediment basins
- Green Level West to I-540: Completed diamond grinding lane 1 Northbound
- Carpenter Fire Station: Installed storm drainage, placed and graded ABC
- Green Level West: Placed asphalt, graded for curb and gutter, placed median islands
- Jenks Rd to Roberts Rd: Continued excavation of mainline, installed underdrains, installed storm drain
- Kelly Rd: Placed embankment
- US 64: Paved asphalt on EB, installed guardrail on WB
- Olive Chapel to US 64: Paved asphalt loops B and C
- Beaver Creek Commons: Placed base asphalt
- Apex BBQ to Beaver Creek Bridge: Placed expressway gutter. Finished mainline PCCP handpour to tie into Site 11 Bridge
- Old US 1 to Apex BBQ: Poured aprons on drop inlets
- US 1 to Old US 1: Began fine grading southbound lanes
- US 1: Excavating tie-ins of ramp B
- Station 121+00 to US 1: Placed embankment, excavated permanent ditches, began rough grading
- Hwy 55 Bypass to Old Holly Springs Rd: Completed excavation, installed storm drain
- Beginning of Project to Hwy 55 Bypass: Installed storm drainage, drill and blasted rock, placed embankment
STRUCTURES
(Update posted February 2, 2012)
Lighting
- BBH is installing conduit for roadway lighting on the north end at NC55.
- BBH is installing complete with conduit for lighting north at Green Level West.
ITS – ORT
- TCD completed the bore at White Oak Creek and will begin the bore at Nancy Branch this week.
- PEC contractor completed conduit installation to POD’s 10, 11, 12, 12A & 16, to ORT Site 5 and will begin pulling wire this week.
- ORT 5 Building pad complete and building will be delivered the week of 2/13/12.
- ORT 5 gantry columns are in progress.
Bridges Overview
- Site #15 Kelly Rd – Drove H-pile Bent #1 20 EA.
- Site #13 Beaver Creek Commons – Slipped bridge barrier wall and drilled holes for 2 bar rail.
- Site #12 Olive Chapel Rd. over WWF – Poured bridge deck Span B and Diaphragms.
- Site #10 Apex Barbeque – End Bent #1 & #2 MSE walls are in progress. Bent #1 Cap has been formed, poured and stripped. End
- Bent #1 Cap and Backwall has been formed and poured.
- Site #9 Old US1 - End Bent #2 MSE wall is in progress. End Bent #2 Cap is in progress. H-Piles at End Bent #1 have been driven.
- Site #8 CSX - End Bent #2 Damproofing / Waterproofing is in progress. End Bent #1 Backfill Abutment is in progress. End Bent #2
- Backfill Abutment is in progress. Set Span A structural steel girders.
NCDOT Construction Updates for the Western Wake Freeway
- September 30, 2011
- August 26, 2011
- August 22, 2011
- August 15, 2011
- August 8, 2011
- July 29, 2011
- July 22, 2011
- July 15, 2011
- July 8, 2011
- July 1, 2011
- June 24, 2011
Previous Bi-Weekly Updates
|