Construction Updates


Current Project Wide Status 
Week Ending 1/27/12
(updates are published bi-weekly)

Click here to view previous updates

Updated Schedule Progress

(Right: Aerial Photo of US 64 & Kelly Road)

 

  

Click on the thumbnails below to view the enlarged photos. (Updated February 2, 2012)
Roll mouse over the photos before clicking to view description. 


Finishing Mono Island on Kelly Road S. Jughandle Aerial Photo of US 64 & Kelly Road Placing ABC on Carpenter Fire Road Erecting Batch Plant at Old US 1 Yard

Site #10 Apex Barbeque Rd – Forming Cap at Bent #1 Site #8 CSX Railroad – Setting Structural Steel Girders Span A Site #10 Apex Barbeque Rd – Backfilling End Bent #1 MSE Wall Site #8 CSX Railroad – Backfilling End Bent #2 Abutment

 ROADWAYS:
(update posted February 2, 2012) 

 

Bi-Weekly Overview:

  • Robert’s Rd to I-540: Installed guardrail, backed shoulders, removed sediment basins
  • Green Level West to I-540: Completed diamond grinding lane 1 Northbound
  • Carpenter Fire Station: Installed storm drainage, placed and graded ABC
  • Green Level West: Placed asphalt, graded for curb and gutter, placed median islands
  • Jenks Rd to Roberts Rd: Continued excavation of mainline, installed underdrains, installed storm drain
  • Kelly Rd: Placed embankment
  • US 64: Paved asphalt on EB, installed guardrail on WB
  • Olive Chapel to US 64: Paved asphalt loops B and C
  • Beaver Creek Commons: Placed base asphalt
  • Apex BBQ to Beaver Creek Bridge: Placed expressway gutter. Finished mainline PCCP handpour to tie into Site 11 Bridge
  • Old US 1 to Apex BBQ: Poured aprons on drop inlets
  • US 1 to Old US 1: Began fine grading southbound lanes
  • US 1: Excavating tie-ins of ramp B
  • Station 121+00 to US 1: Placed embankment, excavated permanent ditches, began rough grading
  • Hwy 55 Bypass to Old Holly Springs Rd: Completed excavation, installed storm drain
  • Beginning of Project to Hwy 55 Bypass: Installed storm drainage, drill and blasted rock, placed embankment


 

STRUCTURES
(Update posted February 2, 2012
)

 

Lighting

  • BBH is installing conduit for roadway lighting on the north end at NC55.
  • BBH is installing complete with conduit for lighting north at Green Level West.

ITS – ORT

  • TCD completed the bore at White Oak Creek and will begin the bore at Nancy Branch this week.
  • PEC contractor completed conduit installation to POD’s 10, 11, 12, 12A & 16, to ORT Site 5 and will begin pulling wire this week.
  • ORT 5 Building pad complete and building will be delivered the week of 2/13/12.
  • ORT 5 gantry columns are in progress.

Bridges Overview

  • Site #15 Kelly Rd – Drove H-pile Bent #1 20 EA.
  • Site #13 Beaver Creek Commons – Slipped bridge barrier wall and drilled holes for 2 bar rail.
  • Site #12 Olive Chapel Rd. over WWF – Poured bridge deck Span B and Diaphragms.
  • Site #10 Apex Barbeque – End Bent #1 & #2 MSE walls are in progress. Bent #1 Cap has been formed, poured and stripped. End
  • Bent #1 Cap and Backwall has been formed and poured.
  • Site #9 Old US1 - End Bent #2 MSE wall is in progress. End Bent #2 Cap is in progress. H-Piles at End Bent #1 have been driven.
  • Site #8 CSX - End Bent #2 Damproofing / Waterproofing is in progress. End Bent #1 Backfill Abutment is in progress. End Bent #2
  • Backfill Abutment is in progress. Set Span A structural steel girders.